2013 PRE-BOND PLANNING

Our relationship with La Conner School District began in 2011 when we were asked to perform a facility condition assessment of their 6 major academic buildings. All housed on one campus, most of these aging, historical buildings were reaching a critical point where the facilities were nearing the end of their useful life. At the competition of the assessment, the district was presented with a prioritized list of deficiencies, which was used to develop a plan for the subsequent bond.

The project that ultimately rose to the top required swapping program of the elementary school and middle school buildings. Through a series of phased projects on an occupied campus, we worked with the district to modify the new elementary school for the needs of its new population, and then develop a current educational specifications document that would guide the design team as they replaced the middle school in 2015 and prepared for an eventual replacement of the high school.

PROJECT MILESTONES

+ QUICK FACTS

Client:
Project Type:

2011   Facility condition assessment & project prioritization

2011-2012   Bond planning & conceptual estimating 

2013   Study & Survey

2013   Successfully secured a $21M bond

2013   Development of educational specifications for the La Conner Middle School

2014   Completion of addition to La Conner Elementary School

2015  Completion of replacement of La Conner Middle School

2016   Demolition of the Old Gym & Auditorium Repairs

2017   Miscellaneous small projects: exterior siding, roofing + interior finishes at La Conner High School, main entry & commons modernization at La Conner High School, district-wide lighting improvements